Nether Carswell Wind Turbine

Location: 
East Renfrewshire
Project Description: 
Scope:

TNEI Services Ltd has undertaken initial site feasibility for Feed in Tariff scale turbines on over 150 sites across Scotland during 2011 on behalf of Intelligent Land Investments. This was done using a bespoke model tailored specifically to the client’s needs and requirements. On those sites that were suitable for progression to planning, TNEI then prepared and submitted the planning applications.

The Nether Carswell site is located on the outskirts of Neilston and falls within the jurisdiction of East Renfrewshire Council. Consent was granted for a single 500kW wind turbine with a 50m hub height as well as associated infrastructure in January 2012.

 

 

Key Features:
  • Site visits to discuss turbine siting options with landowners
  • Undertaking technical assessments necessary as part of the supporting documentation;
  • Appointing and managing subcontractors where required to conduct specialist assessments;
  • Managing the design of the layout using a constraints mapping process;
  • Production of a supporting statement and figures for the planning application;
  • Managing submission of the planning application and responding to any queries or requests for further information which arose.

 

Key Facts: 
Client: Intelligent Land Investments  
Timescale: 3 months  
Capacity: 500kw  
Outcome: Consented at local level  
Decision Date: January 2012